Evidence before inference
Important facts retain their source, confidence, observation date and interpretation notes. Unknowns remain visible.
The rules behind money, status, responsibility and evidence.
Important facts retain their source, confidence, observation date and interpretation notes. Unknowns remain visible.
Budget provision, sanctions, release, tender value, awarded value, expenditure and audited expenditure are not interchangeable.
People are represented through effective-dated postings. An office does not become a different entity when the officeholder changes.
The government structure helps users browse responsibility and delivery. It is not presented as a complete legal reporting hierarchy.
Missing, stale, conflicting or incomplete information is flagged without corruption allegations or automated risk scores.
Statewide navigation can exist before detailed evidence. Unpopulated branches say Coverage pending.
A completion date is recorded.
Not completed, and the planned finish has passed, or the office's latest finish estimate is after the planned finish, or the planned start has passed with no start recorded. A late work that has not started is shown in red.
Started or not yet due to start, and none of the late conditions apply.
No planned dates are available, so we do not say whether it is on time. Most official tender records are in this state today.
The office should update a work weekly if it runs up to 2 months, monthly up to 8 months, and quarterly beyond. An update older than that is listed under Needs attention.
Out of 5: the share of projects with known dates that are completed or on time, multiplied by 5. Projects without public dates are left out, not counted against anyone.
Not collected yet, so not rated. Sample ratings appear only when sample data is switched on.
The average of the areas that have a rating. The number of areas used is always shown.
Made-up works that show the flow. Every one is marked Sample, never linked to a named officer, and hidden unless sample data is switched on.
Names come from official Tamil Nadu government pages, with the source link and the date checked. District in-charge ministers come from a news report of the official announcement, and say so. Responsibility is shown by post, not as a claim about any person.
Each work has a short checklist. A step is done on a date, or not done. Green means done. Yellow means not done and not yet due. Red means not done and past its due date. When a step is late, every later step and the finish move back by the same days. The project is red if any step is red, and green when all are done.
The time limits come from the CPWD rules. These are central rules, so we use them as the benchmark, not as a Tamil Nadu rule. Where the limit is our own reading, it says Aakalan rule. Sample works show sample checkpoints. Real works show none until the office records them.
Work starts on the date set in the contract, or when the site is handed over, whichever is later.
Official rule. All works. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 5
The rule says within 7 working days of award. Aakalan does not store the award date yet, so it counts 7 days from the planned start.
Aakalan rule. All works. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 5.1(i)
The rule says a report for the past month by the 5th of each month. Aakalan sets the first one at 35 days after the planned start.
Aakalan rule. Works longer than 2 months. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 5.1(iv)
Within 10 days of completing the work. Counted from the planned finish.
Official rule. All works. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 8
The engineer inspects within 30 days of the notice. That is 40 days after the planned finish.
Official rule. All works. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 8
Within 3 months of completion, or 1 month after the certificate, whichever is earlier. That is 70 days after the planned finish.
Official rule. All works. CPWD benchmark. CPWD General Conditions of Contract 2023, clause 9
No time limit in the rules.
Minimum 15 or 30 days for bids, but Aakalan does not store the tender date yet.
90 days from bid opening. The opening date is not stored yet.
The day count is set in each tender document.
Not found in any official current text, so not used.